KUALA LUMPUR: Some 36 rural water supply projects in Sabah and Sarawak, with a combined cost of over RM1.6bil have been delayed by up to seven years...
Vous n'êtes pas connecté
KUCHING: The Auditor-General's Report 2/2024 found discrepancies in the allocation balances for the Rural Water Supply Project (BALB) in Sarawak and Sabah in 2017 and 2020, as reported in the Budget Program and Performance Report by the Ministry of Rural and Regional Development (KKDW).
KUALA LUMPUR: Some 36 rural water supply projects in Sabah and Sarawak, with a combined cost of over RM1.6bil have been delayed by up to seven years...
KUALA LUMPUR: The Auditor General’s Report (LKAN) 2/2024 has proposed 64 audit recommendations for implementation by ministries, departments,...
KUALA LUMPUR: The Human Resources Ministry has submitted a report to the Malaysian Anti-Corruption Commission (MACC) regarding issues highlighted in...
SERDANG: A team led by the secretary-general of the Energy Transition and Water Transformation Ministry (Petra) will address the delays in 145 out of...
KUALA LUMPUR: Reports detailing the findings in the Auditor General’s Report and Public Accounts Committee (PAC) will be submitted to the Malaysian...
DEADLINE ON: 22-JUL-2024 15:00 0.00UNITED NATIONS OFFICE FOR PROJECT SERVICES (UNOPS)INVITATION TO BID FOR SUPPLY AND DELIVERY OF VEHICLES TO THE...
The Belize Social Investment Fund (BSIF) and the Ministry of Rural Transformation, Community Development, Labour & Local held the groundbreaking...
KUCHING: The Federal Government's decision to exempt Sarawak and Sabah from the diesel subsidy rationalisation exercise was not due to demands from...
KUALA LUMPUR: The River of Life (RoL) project is expected to be delayed and will not meet its deadline this year, according to the Auditor-General’s...