The liquefied natural gas terminal at Vasiliko will be completed, Energy Minister George Papanastasiou promised on Tuesday. Addressing the House...
Vous n'êtes pas connecté
The government is awaiting legal advice after the European Commission demanded the return of €67 million it had paid for the Vasiliko liquefied natural gas (LNG) terminal that was never completed, Energy Minister George Papanastasiou said on Friday. The Law Office of the Republic has sought advice from British experts and then “we will decided […]
The liquefied natural gas terminal at Vasiliko will be completed, Energy Minister George Papanastasiou promised on Tuesday. Addressing the House...
The government is now pondering its options for appeal after the European Commission gave it until November 6 to repay a total of €67.2 million...
Returning to the European Commission the €67 million linked to the stalled LNG project will not “derail” this year’s state budget, the...
The Republic of Cyprus will pay the €25 million demanded of it by Greece’s independent transmission system operator (Admie) when the Great Sea...
Cyprus on Wednesday officially launched its long-awaited competitive electricity market, which Energy Minister George Papanastasiou said should...
Akel on Friday blasted the government of former president Nicos Anastasiades for “criminally erroneous and suspicious decisions” and of incumbent...
VANCOUVER — Two legal challenges filed in British Columbia claim a liquefied natural gas pipeline hasn't been "substantially started," contrary to a...
VANCOUVER — Two legal challenges filed in British Columbia claim a liquefied natural gas pipeline hasn't been "substantially started," contrary to a...
VANCOUVER — Two legal challenges filed in British Columbia claim a liquefied natural gas pipeline hasn't been "substantially started," contrary to a...
VANCOUVER — Two legal challenges filed in British Columbia claim a liquefied natural gas pipeline hasn't been "substantially started," contrary to a...